Power Up: DLP-507 363-205-401
Page 4 of 10 Issue 7, March 1997
19. Reseat another
BATTERY CHARGER
while observing indicators on
BAT-
TERY CHARGER
faceplate.
Response:
BAT DISCHG
indicator will light and remain lighted for a
period of time determined by charge state of batteries.
If
BAT DISCHG
indicator remains lighted for more than 4
minutes,
BCU PMN
(or
P/M
) and
ADU NE
indicators will also
light.
When
BAT DISCHG
indicator goes off, the
HIGH RATE
CHG/ON
indicator will light and, if
BCU PMN
(or
P/M
) and
ADU NE
indicators are lighted, they will go off after 4 min-
utes.
The
HIGH RATE CHG/ON
indicator will go off after a period
of time determined by charge state of batteries.
Repeat from Step
2.
20. Reseat all
BATTERY CHARGER
s.
21.
!
CAUTION:
Removing AC power from a working system will cause a transfer to
battery supply, bring up a CO alarm, and eventually cause a service
interruption.
Turn off circuit breaker providing AC power to system under test.
Response:
BAT DISCHG
indicators on all
BATTERY CHARGER
s are
lighted.
ALARM
indicators on all
336A RECTIFIER
s are
lighted.
22. Condition DMM to measure DC volts.
23. Connect DMM test leads to
GND
jack and
48L
jack on
LDU
.
24. Does DMM indicate between 42 and 56 volts?
If
YES,
then proceed to Step
29.
If
NO,
then continue with Step
25.
25. Connect DMM test leads to
GND
jack and
48B
jack on
LDU
.
26. Does DMM indicate between 42 and 56 volts?
If
YES,
then continue with Step
27.
If
NO,
then proceed to Step
28.