363-205-401 Acceptance: Introduction-000
Issue 7, March 1997 Page 3 of 4
SUMMARY
The basic acceptance procedures are listed below:
Verify that the RT enclosure has been installed and spliced.
Verify that all equipment shelves are mounted securely and are not damaged.
Look for misaligned, dented, or twisted shelves and bent or broken slot connec-
tors of front of equipment shelf.
Look for bent, broken, or crossed terminals and pins if backplane is accessible.
Verify that the circuit pack(s) can be installed in the shelf if plug-in circuit packs
for the shelf equipment are available. Remove all circuit packs installed.
Verify power panel circuit breaker (fuses in a 51-type cabinet) can be turned on
without tripping the breakers. Verify proper AC voltage at each outlet jack on the
power panel. Use an AC circuit tester at power panel outlet jacks and verify AC
power has been spliced in correctly.
Verify power cord connections to the power panel per label inside the side 1
door.