363-205-401 Power Up: Introduction-000
Issue 7, March 1997 Page 1 of 8
Turn Up Power Plant for Series 5 RT
Introduction
Introduction
This Tab provides procedures to equip and power up the various types of power
shelves used in
SLC
Series 5 carrier system remote terminal (RT) enclosures. The
procedures include installation of batteries, rectifier units, battery charger units, and
ringing generator units. The purpose of these procedures is to provide power and
ringing current prior to the turnup of the
SLC
Series 5 carrier system dual RT channel
bank Assembly. Procedures to add battery strings to an equipped RT enclosure are
included.
New bulk power cabinets may be equipped with 4A fan units. The 4A fan has a built
in control unit and does not require the AUA24 Fan Control Unit (FCU) in the RT
channel bank. The 4A fan unit will be functional when the power shelf is equipped.
This Tab section provides procedures to test the 4A fan.
NOTE:
The discontinued availability 80C cabinet (Phase 0) used
SLC
96 1B (1A) power
and jack panel, 3B battery charger, and 128A apparatus mounting battery
shelves. Refer to 363-202-401 to establish power for this equipment.
The following is a list of currently available power and ringing equipment:
J1C182BA - Distributed Power Shelf
This power shelf can be in 51A cabinets, 80-type cabinets, 90-type cabinets,
and frame RT enclosures.