Conversions: DLP-519 363-205-401
Page 4 of 4 Issue 7, March 1997
31. Use RT schematic drawing SD-7C118-01 to check wiring. Check for tip and
ring reversal between RT and cross-connect terminal. Correct wiring problem
and repeat Step
25
until tests pass and continue with Step
32.
32. Is this the last designated channel to be tested with TBCU?
If
YES,
then continue with Step
33.
If
NO,
then proceed to Step
25.
33. At RT, remove test telephone and reinstall the protector unit for the customer
drop.
STOP. YOU HAVE COMPLETED THIS PROCEDURE.