363-205-401 Power Up: NTP-006
Issue 7, March 1997 Page 3 of 4
DO ITEMS BELOW IN ORDER LISTED FOR DETAILS, GO TO
10. Turn on each power shelf DC circuit breaker and verify that they
do not trip. If a circuit breaker does trip, cabinet wiring trouble
must be cleared before continuing.
11. Turn off AC circuit breaker and verify
BOD
on
AUG4 BIU
and
ALARM
on
336A
indicators light (may take up to 5 minutes).
Replace unit if indicator does not light.
12. If the power shelf powers an RT dual channel bank, continue with
Step
13
. Otherwise, proceed to Step
15
.
DLP-51113. Install and test
PCU
, then remove
PCU
; in dual RT channel bank
facility (middle) shelf.
14. Repeat Steps
13
for each RT channel bank. Then continue with
Step
15
.
15. Turn on AC circuit breakers.
16. Update office records.