the pressure can’t achieve ‐0.1Mpa after pumping 50 minutes, pleasecheckiftherearesomeleakage
points.
Fully close the handle Lo valve of the manifold valve and stop the operation of the vacuum pump. 
Confirm that the gauge needle does not move (approximately 5 minutes after turning off the vacuum 
pump). 
7)  Turn the flare nut of the 3-way valves about 45° counterclockwise for 6 or 7seconds after the 
gas 
coming  out,  then  tighten  the  flare  nut  again.  Make  sure  the  pressure  display  in  the  pressure 
indicator is a little higher than the atmosphere pressure. Then remove the charge hose from the 3 
way valve. 
8)  Fully open the 2 way valve and 3 way valve and securely tighten the cap of the 3 way valve. 
2. Air purging by refrigerant 
 
Procedure: 
1). Confirm that both the 2-way and 3-way valves are set to the closed position. 
2). Connect the charge set and a charging cylinder to the service port of the 3-way valve.   
3). Air purging. 
Open the valves on the charging cylinder and the charge set. Purge the air by loosening the 
flare nut on the 2-way valve approximately 45’ for 3 seconds then closing it for 1 minute; repeat 3 
times. 
After purging the air, use a torque wrench to tighten the flare nut on the 2-way valve. 
4). Check the gas leakage. 
Check the flare connections for gas leakage.