R410A 50Hz Tropical Split AC MCAC-UTSM-2012-12
128
The distance of the foundation bolt is shown in Fig-17.
762
676
Fig-17
3.3 Convey Outdoor Unit
Use 4 steel ropes of a Ф6mm or bigger size to hoist the outdoor unit and convey it into the room.
In order to prevent scratch and deformity the outdoor unit, apply a guard board to the surface of contact
between the steel ropes and the air conditioner.
Remove the cushion for use in the transport after finishing the transport. (Fig-18)
Fork truck can be used for conveying.
Steel wire
Guard board
Base and bracket
Holes for fork truck
Fig-18
3.4 Snow protection facilities must be installed in the snowfall areas. (Fig-19)
In case the snow protection facilities are incomplete, faults may occur. In order to prevent influence
caused by snow, set up raised pavilion, and install snow protection sheds at the air inlet and air outlet.

Other manuals for Midea MTA-76CRN1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Midea MTA-76CRN1 and is the answer not in the manual?

Midea MTA-76CRN1 Specifications

General IconGeneral
BrandMidea
ModelMTA-76CRN1
CategoryAir Conditioner
LanguageEnglish

Related product manuals