optic cables.
4. If the power supplies were unplugged, plug them back in and reinstall the power cable retainers.
5. Complete the reinstallation of the controller module:
a. Firmly push the controller module into the chassis until it meets the midplane and is fully seated.
The locking latches rise when the controller module is fully seated.
Do not use excessive force when sliding the controller module into the chassis to avoid
damaging the connectors.
The controller module begins to boot as soon as it is fully seated in the chassis.
b. Rotate the locking latches upward, tilting them so that they clear the locking pins, and then lower them
into the locked position.
c. If you have not already done so, reinstall the cable management device.
d. Halt the controller at the LOADER prompt.
6. Reset the time and date on the controller:
a.
Check the date and time on the healthy controller with the
show date command.
b. At the LOADER prompt on the target controller, check the time and date.
c.
If necessary, modify the date with the
set date mm/dd/yyyy command.
d.
If necessary, set the time, in GMT, using the
set time hh:mm:ss command.
e. Confirm the date and time on the target controller.
7.
At the LOADER prompt, enter
bye to reinitialize the PCIe cards and other components and let the
controller reboot.
8.
Return the controller to normal operation by giving back its storage:
storage failover giveback
-ofnode impaired_node_name
9.
If automatic giveback was disabled, reenable it:
storage failover modify -node local -auto
-giveback true
Step 7: Return the failed part to NetApp
Return the failed part to NetApp, as described in the RMA instructions shipped with the kit. See the
Part Return
& Replacements
page for further information.
AFF A900 systems
Install and setup
Start here: Choose your installation and setup experience
You can choose from different content formats to guide you through installing and setting
up your new storage system.
•
Quick steps
682