EasyManua.ls Logo

Orenco AdvanTex AX20-RT User Manual

Default Icon
20 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
Installation Manual
NIM-ATX-AXRT-1
Rev. 1.0, © 1/10
Orenco Systems
®
, Inc.
AdvanTex
®
-AX20-RT
Treatment Systems
An illustrated guide to installing
an Orenco AdvanTex
®
AX20-RT
Treatment System.
®
800-348-9843
541-459-4449
www.orenco.com
www.vericomm.net
Orenco Systems
Incorporated
Changing the Way the
World Does Wastewater
®
Residential Applications
Question and Answer IconNeed help?

Do you have a question about the Orenco AdvanTex AX20-RT and is the answer not in the manual?

Orenco AdvanTex AX20-RT Specifications

General IconGeneral
BrandOrenco
ModelAdvanTex AX20-RT
CategoryWater Filtration Systems
LanguageEnglish

Summary

Before You Begin

Conditions for AX20-RT Existing System Repair

Requirements for using the AX20-RT system to upgrade or repair an existing septic system.

Key Installation Notes and Warnings

Important considerations and warnings regarding installation and system components.

AdvanTex® AX20-RT System Overview

System Components and Operational Flow

Description of the system's 10 main functional areas and how they work together.

AdvanTex® AX20-RT Installation Procedure

Step 1: Site Plan Review and Sketching

Familiarize yourself with site plans and sketch installation details.

Step 2: Septic Tank Excavation and Setting

Procedures for excavating and properly positioning the septic tank.

Step 3: Riser Installation and Septic Tank Water Test

Guide to installing risers and performing a water test on the septic tank.

Step 4: Effluent Filter Installation

Instructions for installing the effluent filter onto the septic tank's outlet pipe.

Step 5: AX20-RT Unit Excavation and Setting

Detailed steps for excavating and setting the AX20-RT treatment unit.

Step 6: Counterbuoyancy Preparation and Installation

Measures to ensure unit stability in sites with high groundwater.

Step 7: Partial Backfilling of AX20-RT Excavation

Procedure for partially backfilling around the AX20-RT unit with water support.

Step 8: AX20-RT Unit Watertightness Testing

Method for testing the watertight integrity of the AX20-RT unit after partial backfill.

Step 9: Transport Line and Passive Air Vent Connection

Connecting the transport line and installing the passive air vent.

Step 10: Control Panel Installation and Testing

Instructions for installing and verifying the function of the control panel.

Step 11: System Functionality Testing

Procedures for testing the recirc pump, discharge pump, and overall system operation.

Step 12: Final Backfilling Completion

Final backfilling of the excavation around the unit and septic tank.