32 
1. To cut
Bar
0 - 0.5 mm
Copper pipe
Handle
Bar
Yoke
Core
Red arrow mark
Clamp handle
3. To flare
Pipe
Reamer
Point down
2. To remove burrs
Improper flaring
Uneven
thickness
Inclined
Surface
damaged
Cracked
When properly flared, the internal surface
of the flare will evenly shine and be of
even thickness. Since the flare part
comes into contact with the connections,
carefully check the flare finish.
Lo
OPEN
Vacuum pump adaptor
Vacuum
 pump
GAS SIDE
Liquid side
Indoor unit
GAS SIDE
Liquid side
Indoor unit
Hi
CLOSE
THREE-WAY VALVE
THREE-WAY VALVE
THREE-WAY VALVE
THREE-WAY VALVE
Outdoor unit
12.3.2.2  Connecting the piping to outdoor unit 
Decide piping length and then cut by using pipe cutter. Remove burrs from cut edge. Make flare after inserting the 
flare nut (locate at valve) onto the copper pipe. Align center of piping to valves and then tighten with torque wrench 
to the specified torque as stated in the table. 
 
12.3.2.3  Cutting and flaring the piping 
1.  Please cut using pipe cutter and then remove the burrs. 
2.  Remove the burrs by using reamer. If burrs are not removed, gas leakage may be caused. Turn the piping 
end down to avoid the metal powder entering the pipe. 
3.  Please make flare after inserting the flare nut onto the copper pipes. 
 
 
12.3.3  Evacuation of the Equipment 
WHEN INSTALLING AN AIR CONDITIONER, BE SURE TO EVACUATE THE AIR INSIDE THE INDOOR UNIT 
AND PIPES in the following procedure.  
 
1.  Connect a charging hose with a push pin to 
the Low side of a charging set and the 
service port of the 3-way valve. 
o  Be sure to connect the end of the 
charging hose with the push pin to the 
service port. 
2.  Connect the center hose of the charging 
hose of the charging set to a vacuum pump. 
3.  Turn on the power witch of the vacuum pump 
and make sure that the needle in the gauge 
moves from 0cmHg (0MPa) to -76cmHg (-
0.1MPa). Then evacuate the air 
approximately ten minutes. 
4.  Close the Low side valve of the charging set 
and turn off the vacuum pump. Make sure 
that the needle in the gauge does not move 
after approximately five minutes. 
Note: BE SURE TO FOLLOW THIS 
PROCEDURE IN ORDER TO AVOID 
REFRIGERANT GAS LEAKAGE. 
5.  Disconnect the charging hose from the 
vacuum pump and from the service port of 
the 3-way valve. 
6.  Tighten the service port caps of the 3-way 
valve at torque of 18N.m. with a torque 
wrench. 
7.  Remove the valve caps of both of the 2-way 
valve and 3-way valve. Position both of the 
valves to “OPEN” using a hexagonal wrench 
(4mm). 
8.  Mount valve caps onto the 2-way valve and 
the 3-way valve. 
o  Be sure to check for gas leakage.