11.3 Outdoor Unit 
11.3.1  Install the Outdoor Unit 
  After selecting the best location, start installation according to Indoor/Outdoor Unit Installation Diagram. 
1  Fix the unit on concrete or rigid frame firmly and horizontally by bolt nut (ø10 mm). 
2  When installing at roof, please consider strong wind and earthquake. 
Please fasten the installation stand firmly with bolt or nails. 
 
B
C
D
 
Model  A  B  C  D 
UE9***, UE12*** 
PE9***, PE12*** 
570 mm  105 mm  18.5 mm 320 mm 
UE18***  540 mm  160 mm  18.5 mm 330 mm 
11.3.2  Connect the Piping 
11.3.2.1  Connecting the Piping to 
Indoor 
Please make flare after inserting flare nut (locate at 
joint portion, of tube assembly) onto the copper pipe. 
(In case of using long piping) 
Connect the piping 
  Align the center of piping and sufficiently tighten 
the flare nut with fingers. 
  Further tighten the flare nut with torque wrench in 
specified torque as stated in the table. 
 
 
Do not overtighten, overtightening may cause gas leakage. 
 
Piping size  Torque 
6.35 mm (1/4”)  [18 N•m (1.8 kgf•m)] 
9.52 mm (3/8”)  [42 N•m (4.3 kgf•m)] 
12.7 mm (1/2”)  [55 N•m (5.6 kgf•m)] 
15.88 mm (5/8”)  [65 N•m (6.6 kgf•m)] 
19.05 mm (3/4”)  [100 N•m (10.2 kgf•m)] 
11.3.2.2  Connecting the Piping to 
Outdoor 
Decide piping length and then cut by using pipe cutter. 
Remove burrs from cut edge. 
Make flare after inserting the flare nut (located at valve) 
onto the copper pipe. 
Align center of piping to valves and then tighten with 
torque wrench to the specified torque as stated in the 
table. 
 
Torque
wrench
Spanner
or Wrench