- Never turn on the power supply until all installation work has been 
completed.
- Turn on the circuit breaker before test operation extends past 12 
hours. / (The crankcase heater will be energized, which will warm 
the compressor and prevent liquid compression.)
- For three-phase models, check that the phase is not reversed. / (If 
the phase is reversed, the LED on the printed circuit board will 
flash.)
- Check that the voltage is 198 V or higher when starting the unit. 
(The unit will not operate if the voltage is less than 198V.)
- Carry out test operation for 5 minutes or more, using the remote 
control or the switch on the outdoor unit printed circuit board.
- Always carry out cooling operation first during test operation, even 
during the warm season. / (If heating is carried out first, problems 
with operation of the compressor will result.)
22.2. Test operation from the outdoor unit
During outdoor unit emergency operation or test operation, the LEDs on the printed circuit 
board will flash.
To cancel test operation, press the TEST RUN button once more while test operation is being 
carried out. / (Test operation will stop automatically after 30 minutes have passed.)
22.3. Test operation using the wired remote control
115