7.7 Burst Valve Test Procedure Access EA & AccessEAB
7
Installation
7.7 Burst Valve Test Procedure Access™ EA & Access EAB
S
et Burst
Valves To 0.5mm With a Set Of Feeler Gauges
( ensure lift is lowered To ground & Fully depressurised )
Connect Crash Test Kit To Lift
Re-pressurise lift & Operate to Full Stow Height
(Create Safe Area For Testing & Check The Area Is
Clear)
Keeping a Safe
Distance From The Lift.
Open the Crash Test
Valve
Close Crash Valve & Deploy The Lift
Add 25Kg To End Of The Platform
Keeping a Safe
Distance From Lift.
Open the The Crash
Test Valve
Lift Should Stop Or Lower At A
Controlled Speed (adjust Gap To
Suit)
Lift Should Stop Or Lower At A
Controlled Speed (adjust Gap To
Suit)
ADJUST VALVE GAP
To 0,5MM
25kg
25kg