EasyManuals Logo

PLS Access EA Series User Manual

PLS Access EA Series
67 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #25 background imageLoading...
Page #25 background image
7
Installation
7.7 Burst Valve Test Procedure Access EA & AccessEAB
7
Installation
7.7 Burst Valve Test Procedure Access™ EA & Access EAB
S
et Burst
Valves To 0.5mm With a Set Of Feeler Gauges
( ensure lift is lowered To ground & Fully depressurised )
Connect Crash Test Kit To Lift
Re-pressurise lift & Operate to Full Stow Height
(Create Safe Area For Testing & Check The Area Is
Clear)
Keeping a Safe
Distance From The Lift.
Open the Crash Test
Valve
Close Crash Valve & Deploy The Lift
Add 25Kg To End Of The Platform
Keeping a Safe
Distance From Lift.
Open the The Crash
Test Valve
Lift Should Stop Or Lower At A
Controlled Speed (adjust Gap To
Suit)
Lift Should Stop Or Lower At A
Controlled Speed (adjust Gap To
Suit)
ADJUST VALVE GAP
To 0,5MM
25kg
25kg

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the PLS Access EA Series and is the answer not in the manual?

PLS Access EA Series Specifications

General IconGeneral
BrandPLS
ModelAccess EA Series
CategoryLifting Systems
LanguageEnglish