Check lift to order supplied by PLS
Dispose of any excess parts / materials appropriately
Lift to be collected in a timely manner
If lifts cannot be collected and delivered for any reason, PLS will dispatch
lift to the customer’s premises (UK ONLY)
Ensure enough time is allowed to install the lift in one full day
To sign in / register with relevant manager at Coach Builders, and abide by
the Site’s H & S Policy.
Dependent on the Customer’s H & S Policy, the Engineer maybe required
to provide a working on site risk assessment
Deliver the lift (s), plus tooling and test weights
To co-ordinate lift, tooling and weights to the installation bay
For the given vehicle, Engineer to check correct paperwork
Check vehicle is (Standard), anything other than (Standard) should be
reported immediately. This includes spare wheels, fuel tank, modification
of suspension, air conditioning unit, exhaust and all parts of exhaust
Installation should commence in correlation to guidelines set out by PLS
Hand control cable through door – Vehicle cable bush
Door plug (Nutrik) 20mmø hole required. (If fitted through Door)
Door switch 12mmø hole. One required if no cab switch?
Rubber boot on battery terminals.
Inside the Vehicle shims must be used to ensure Base is fitted flat.
Ensure the Base is correctly bolted into place using the PLS universal
fitting plates secured from below the chassis-DO NOT use washers.
Once lift is installed and correctly adjusted, Loler inspection certificate to
be completed. A full weight test to be conducted in accordance with the
weight certificate. (BS:EN 1756-2-2004 15 minute creep test)
First weight test to be tested to 125% stated S.W.L load (I.e. 400kgs =
500kgs full test). Photographs are to be taken of the weight applied
A final check must be made to ensure that the pump is set between
400kgs < 425kgs max
7.9
Installation Check List
Access™ EA & Access™ EAB
7
Installation
7.9 Installation Check List Access™ EA & Access™ EAB