6
Installation Instructions
H910 Splice and Tee Kit
17a
For all installations
except
gutter/downspout
17b
For H612 and H622 gutter/downspout installations
16a
For H612 and H622 heating cables only
16b
For H311, H611, and H621 heating cables only
Shrink the tube completely. Start at end
farthest from the cap and work toward the
open end.
• Keep heating after tube has shrunk, to melt
adhesive and mastic inside tube. Total heating
time should be about 5 minutes.
Shrink the tube completely. Start at end
farthest from the cap and work toward the
open end.
• Keep heating after tube has shrunk, to melt
adhesive and mastic inside tube. Total heating
time should be about 5 minutes.
• Immediately after shrinking,
pinch the end of the tube with
needle nose pliers until the
end stays sealed; this
normally takes
10 seconds.
• After the connection has cooled, fold
over the connection and fasten it with
the third cable tie.
• Secure heating cable with downspout
hanger (H904).
• Fasten clamp tie to center of connection.
• Use a hammer, nail, and clamp tie to secure
connection and keep it off the gutter bottom
as shown.
• Immediately after shrinking,
pinch the end of the tube with
needle nose pliers until the
end stays sealed; this
normally takes
10 seconds.
Caution:
To avoid burns, allow
heated sections to cool
before touching.
Caution:
To avoid burns, allow
heated sections to cool
before touching.
Secure end of
connection to
heating cable.