EasyManuals Logo

Siemens LGA63.191A27 Datasheet

Siemens LGA63.191A27
11 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #3 background imageLoading...
Page #3 background image
3/11
Siemens Building Technologies CC1N7418en
HVAC Products 08.04.2004
Electrical connection of ionization probe
It is important to achieve practically disturbance- and loss-free signal transmission:
Never run the detector cable together with other cables
– Line capacitance reduces the magnitude of the flame signal
– Use a separate cable
Observe the permissible length of the detector cable (refer to «Technical data»)
The ionization probe is not protected against electric shock hazard
Locate the ionization probe such that the ignition spark cannot arc over (risk of
electrical overloads)
Always run the high-voltage ignition cables separate from the unit and other cables
while observing the greatest possible distances
The insulation resistance between ionization probe and ground must be a minimum
of 50 M, even after a large number of operating hours.
Prerequisite for this is not only high quality heat-resistant insulation of the cable,
but also of the ionization probe itself (ceramic holder!)
A soiled ionization probe holder offers favorable conditions for surface leakage cur-
rents which reduce the magnitude of the flame signal
The burner (as the counter-electrode) must be correctly earthed, or else no ioniza-
tion current will flow
Earthing the boiler alone does not suffice!
The connection diagrams shown apply to burner controls with earthed neutral con-
ductor. In the case of ionization current supervision in networks with nonearthed
neutral conductor, terminal 2 must be connected to the earth conductor via an RC
unit (part no. ARC 4 668 9066 0). In that case, it must be made certain that the
relevant national safety regulations are complied with (e.g. electric shock hazard
protection), since AC 230 V / 50 Hz mains voltage results in a leakage current of
2.7 mA
Commissioning notes
Prior to commissioning, check to ensure that wiring is in an orderly state
When commissioning the plant or when doing maintenance work, make the follow-
ing safety checks:
Safety check Anticipated response
a) Burner startup with no flame signal; for
that purpose, open the connection be-
tween burner control and ionization
probe prior to burner startup and main-
tain that status
Lockout at the end of «TSA»
b) Burner operation with simulated loss of
flame during operation; for that purpose,
open the connection between burner
control and ionization probe during
burner operation and maintain that
status
Restart, followed by lockout at the
end of «TSA»
c) No air pressure signal during «t1» (only
with LGA52... / LGA63... with fan)
No startup
d) Air pressure failure during operation
(only with LGA52... / LGA63... with fan)
Shutdown

Other manuals for Siemens LGA63.191A27

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens LGA63.191A27 and is the answer not in the manual?

Siemens LGA63.191A27 Specifications

General IconGeneral
BrandSiemens
ModelLGA63.191A27
CategoryController
LanguageEnglish

Related product manuals