Building Technologies 74 319 0618 0 a 17.04.2008 41/276
en
11 Holiday period -
(1…8)
……..................
12 Date of first day of
holiday
--.--
(01.01 … 31.12)
……..................
Day.Month
13 Date of last day of
holiday
--.--
(01.01 … 31.12)
……..................
Day.Month
14 Heating curve, flow
setpoint at 15 °C
outside temperature
30 °C
(20…70)
…...............°C
15 Heating curve, flow
setpoint at –5 °C
outside temperature
60 °C
(20…120)
…...............°C
These operating lines are active
only if digital adjustment of the
heating curve has been se-
lected (refer to entry made on
operating line 73)
26 Setpoint d.h.w.
temperature
NORMAL
55 °C
(20…100)
…...............°C
27 D.h.w. temperature Display function
28 Setpoint d.h.w.
temperature
REDUCED
40 °C
(8…80)
…...............°C
With plant types x–0 and x–5,
these operating lines do not
appear
31 Weekday (for swit-
ching program 2)
1-7
(1…7)
…......................
1 = Monday
2 = Tuesday, etc.
1-7 = entire week
32 Start of first ON
period
05:00
(00:00…24:00)
…......................
33 End of first ON
period
22:00
(00:00…24:00)
…......................
34 Start of second ON
period
--:--
(00:00…24:00)
…......................
35 End of second ON
period
--:--
(00:00…24:00)
…......................
36 Start of third ON
period
--:--
(00:00…24:00)
…......................
37 End of third ON
period
--:--
(00:00…24:00)
…......................
Switching program 2
--:-- = period inactive