DC INVERTER U-MATCH AIR CONDITIONERS INSTALLATION
1.3.5 Installation Clearance Data
Figure 1-3-6
Models H(mm)
ASC-18AI
230
ASC-24AI
260
ASC-36AI ASC-36AI S
ASC-42AI ASC-42AI S
320
1.3.6 Drain Piping Work
1
Installation of Drainage Pipeline
When connecting the drainage pipe with the unit, do not apply excessive force to the pipeline at the
side of the unit. The fixing position of the pipeline shall be near the unit.
Purchase general-purpose hard PVC pipe locally to be used as the drainage pipeline. When
carrying out connection, place the end of the PVC pipeline into the drainage hole. Use flexible
drainage tube and tighten it with thread loop. Never use adhesive to connect the drainage hole and
the flexible drainage tube. (As shown in Figure 1-3-7)
When the laid drainage pipe is used for multiple units, the common pipe shall be about 100mm
lower than the drainage outlet of each set of unit. A pipe with thicker wall shall be used for such
purpose.