5 LCS tool SMA Solar Technology AG / SMA Solar Technology America LLC
18 IMVIOBOX-IA-xx-12 Installation Manual
Figure 5.8 LCS tool - list of all inverters connected to the Inverter
Manager
12. If sufficient PV power is present and the grid code
conditions are met, the inverter starts the operation.
13. During commissioning it is possible to download a
commissioning report in the Reports menu. The report
contains information about inverter settings, including
actual disconnection values for each inverter.
By clicking the folder icon in the menu Reports, it is
possible to open a folder for commissioning reports
(incl. grid code information). See figure 5.9.
Figure 5.9 LCS tool - commissioning report