Installing the unit
When the oven has been positioned do a final check and make sure doors when opened clear any sur-
faces bench, wall or any other obstruction.
Roastrunner oven is to be connected to a AC3 Phase + Earth power supply. Oven supplied with 2M lead
and a 5 pin plug. Double oven 50A IP56 - Single 32A. Where more than one outlet is available for the
oven, always check rotation is unchanged should socket be changed.
An all-pole electrical isolation switch should be mounted on the wall and be fully accessible to the opera-
tor. It should be mounted 1.5m above the floor as a recommended height.
Oven to drain to a Tundish in floor. Connect drainage piping - must have fall so the water runs downhill
to the drain. If plumbing does not have fall the fat separator cannot function properly. Contact Tech-
nobake if no Tundish.
Connect water to the oven. Cold water only and tap fully open to allow maximum water flow. Tie or coil
all water hoses ensuring they are off the ground using cable ties.