Do you have a question about the Thomas & Betts Nexus RF and is the answer not in the manual?
Mechanism for segregating two or more systems in close physical proximity.
Commissioning and 12-month defects liability period support for Nexus RF systems.
Outlines the key stages in designing and implementing a Nexus RF system.
Review site plans and determine total fitting numbers and types early.
Determine the number and optimal locations of Routers based on fitting distribution.
Interconnecting Area Controllers and Routers via an IP network.
Assigning unique SPU ID numbers to each fitting for system identification.
Install each fitting, label with SPU ID, and collect MAC address.
Install the IP backbone with RJ45 patch points and GPOs near Controller locations.
Mount Routers, supply power, and connect to the network after configuration.
Site ready when 90% fittings installed, IP backbone verified, and Routers installed.
Nexus RF specialist performs all commissioning based on network design and spreadsheet.
Begins after commissioning; Thomas & Betts monitors site operation for reliable system operation.
System testing at 6 and 12 month intervals; issues addressed and reports supplied.