instructions for installation
DOUBLE LEAF OPERATION
Perform the mechanical installation and the electric wiring assuming the two leaves would be independent, following page
6 in presence of articulated arm or page 8 sliding arm or page10 elbow arm.
The Double leaf operation has a MASTER and a SLAVE leaf. The MASTER leaf is the rst one to OPEN.
ADDITIONAL CONNECTIONS AND SPECIFIC PARAMETERS SETTING
Connect the MASTER and SLAVE boards
by following the wiring diagram on the right
Make sure the operators are installed cor-
rectly and the door leaves are in CLOSE
position
Set parameter as 1 on MASTER and 2
on SLAVE
Set independently for each wing the pa-
rameters 101,102,103,104,105 (related to
weight, width, wall depth, sensors logic for
activation and safety) as shown in page 21
Following the instructions on page 17, per-
form the learning process of the MASTER
door leaf rst and the SLAVE door leaf
later; during the SLAVE door leaf learning
process, the MASTER one will automati-
cally move to OPEN position.
+24V
Seriale B
GND massa
Seriale A
1
2
3
5
1
2
3
4
5
1
2
3
4
5
SCHEDA ELETTRONIC A
MASTER
SCHEDA ELETTRONIC A
SLAVE
DOUBLE LEAF INSTALLATION
S200
MASTER BOARD
SLAVE BOARD-
*
* view disabled button connection Servo Assisted Manual Opening page 29