EasyManua.ls Logo

Trane TR-OHS RCU Series - Completed Installation Verification Checklist

Trane TR-OHS RCU Series
32 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
SS-SVX004C-EN 31
Appendix A
Forms
Checklist for Completed Installation
Proper clearances for service access have been
maintained around equipment.
Equipment is level and mounting fasteners are tight.
Piping completed to refrigeration equipment.
All field installed piping leak tested.
Refrigerant charge added.
Incoming line voltage matches equipment nominal
namep
lated rating ± tolerances.
Main power wiring connections to the equipment,
i
nclud
ing earth ground, have been properly installed.
Customer supplied main power circuit breaker (HACR
type) o
r fuses have proper ratings for equipment
installed.
Control wiring connections completed to remote
condensi
ng unit.
All wiring connections are tight.
Foreign ma
terials have been removed from inside and
around
all equipment installed (shipping materials,
construction materials, tools, etc.).
Compressor and fan rotate freely withou
t unusual
noise.
Inspect all piping connections for leaks during initial
operation
.

Related product manuals