D400
1/1
MAINTENANCE PROCEDURE FOR D 400 2
nd
STAGE
Question and Answer IconNeed help?

Do you have a question about the Uwatec SCUBAPRO D400 2nd STAGE and is the answer not in the manual?

Uwatec SCUBAPRO D400 2nd STAGE Specifications

General IconGeneral
BrandUwatec
ModelSCUBAPRO D400 2nd STAGE
CategoryController
LanguageEnglish

Summary

Disassembly Procedure

Orifice Replacement Procedure

Break retaining tabs of the orifice with a screwdriver for replacement if needed.

Assembly Procedure

Poppet Assembly Reassembly

Reassemble the poppet with its O-ring, seat, and retainer, ensuring correct orientation and tightening.

Orifice and O-ring Installation

Install the orifice and its O-rings into the housing, aligning locking tabs carefully.

Lever Play Adjustment

Adjust the lever to eliminate play by catching up with the adjustment screw.

Poppet and Housing Assembly Insertion

Insert the poppet and housing assembly into the 2nd stage housing, ensuring correct air outlet orientation.

Lever Alignment Check

Verify the lever is correctly positioned within the diaphragm level, adjusting if necessary.

Adjustment Procedure

Lever Play Setting

Adjust the lever adjustment screw to achieve a total play of 4-5 mm at the lever tip.

Initial Leak Check

Connect to a tank and open the valve to check for leaks after assembly.

Stabilization and Leak-Free Adjustment

Cycle regulator 20 times for stabilization; if no leak, adjust lever play to 3 mm.

Leak Troubleshooting and Spring Adjustment

If leaking, clockwise screw the spring adjustment screw incrementally to stabilize.

Leak Resolution and Lever Adjustment

Adjust lever play to 3 mm after the 2nd stage stops leaking and spring adjustment is stable.

Persistent Leak Troubleshooting

If leaks persist, reverse friction disk or replace poppet assembly/orifice.

Diaphragm Hooking and Alignment

Hook the lever into the diaphragm linkage, aligning injection points for optimal performance.