1
Required material for VENTURA 60 litres
Ÿ M10 attachment set, article no. 1143-00
Ÿ Drilling machine with drill bit ø 10mm
Ÿ Spirit level
Ÿ Socket wrench, SW 17
Figure 2: Bore pattern
Set fixed anchors (see Figure 3). Remove the upper nut along with washer.
Place the container at the desired location and mark out the bore pattern. Alternatively, the bore pattern can be marked out as per Figure 2.
VENTURA 60: Drill ø 10mm holes to a depth of approx. 70mm.
VENTURA 110: Drill ø 12mm holes to a depth of approx. 90mm.
Adjust the lower nut to 25-30mm (the nuts must first be adjusted to the highest point on uneven ground).
Then level out the remaining nuts using the spirit level based on the first nut.
Put the container into position and screw it into place.
Insert the interior container and fix using the securing rod.
Figure 3: Cross-section of attachment
ø10 x 70 / ø12 x 90
25-30 *
45-55 *
* the stated size is only valid at the highest point on uneven ground
Required material for VENTURA 110 litres
Ÿ M12 attachment set, article no. 1145-00
Ÿ Drilling machine with drill bit ø 12mm
Ÿ Spirit level
Ÿ Socket wrench, SW 19
Figure 1: Remove the interior container
Open container, remove securing rod and interior container (Figure 1).
2
3
4
5
6
7
robi-ag.com
ROBI AG Kohlackerstrasse 17 CH-4323 Wallbach +41 (0)61 865 10 10 +41 (0)61 865 10 19
Base assembly for VENTURA 60 / 110 waste bin
15789.2018.01.E.INT
ø10
292
170
(35)
VENTURA 60
240*
(275)
(415)
360*
ø12
380
220
(40)
VENTURA 110
300*
(350)
(500)
460*
* concrete foundation
Question and Answer IconNeed help?

Do you have a question about the Ventura 60 and is the answer not in the manual?

Ventura 60 Specifications

General IconGeneral
BrandVentura
Model60
CategoryGarbage Disposal
LanguageEnglish

Summary

Base Assembly for VENTURA Waste Bins

Required Material for VENTURA 60 Litres

List of required materials for the base assembly of the VENTURA 60 litre waste bin.

Required Material for VENTURA 110 Litres

List of required materials for the base assembly of the VENTURA 110 litre waste bin.

Step 1: Prepare Container

Open the container, remove the securing rod and interior container.

Step 2: Position and Mark

Place the container at the desired location and mark out the bore pattern.

Step 3: Drill Anchor Holes

Drill holes for anchors based on the VENTURA model size (Ø 10mm for 60L, Ø 12mm for 110L).

Step 4: Set Fixed Anchors

Install fixed anchors, removing the upper nut and washer.

Step 5: Adjust and Level Nuts

Adjust lower nuts to 25-30mm and level remaining nuts using a spirit level.

Step 6: Position and Screw Container

Put the container into position and screw it into place.

Step 7: Insert Interior Container

Insert the interior container and fix it using the securing rod.

Post Mounting for VENTURA Waste Bins

Required Material for VENTURA 60 Litres (Post Mount)

Materials needed: strapping system and Allen key for post mounting VENTURA 60.

Required Material for VENTURA 110 Litres (Post Mount)

Materials needed: strapping system and Allen key for post mounting VENTURA 110.

Post Mount Step 1: Prepare Container

Open container, remove securing rod and interior container.

Post Mount Step 2: Loosen Pipe Mounting

Loosen the pipe mounting component.

Post Mount Step 3: Set Pipe Mounting Height

Set the pipe mounting on the rod or candelabra to the desired height.

Post Mount Step 4: Mount Container

Mount the container and screw it into place.

Post Mount Step 5: Insert Interior Container

Insert the interior container and fix it using the securing rod.

Wall Mounting for VENTURA Waste Bins

Required Material for VENTURA 60 Litres (Wall Mount)

Materials: M8 attachment set, drill, spirit level, socket wrench for wall mounting VENTURA 60.

Required Material for VENTURA 110 Litres (Wall Mount)

Materials: M10 attachment set, drill, spirit level, socket wrench for wall mounting VENTURA 110.

Wall Mount Step 1: Prepare Container

Open container, remove securing rod and interior container.

Wall Mount Step 2: Mark Bore Pattern

Mark out the bore pattern in accordance with the diagram.

Wall Mount Step 3: Drill Anchor Holes

Drill Ø 8mm holes for VENTURA 60 and Ø 10mm for VENTURA 110.

Wall Mount Step 4: Set Fixed Anchors

Set fixed anchors into the drilled holes.

Wall Mount Step 5: Position and Screw Container

Put the container into position and screw it into place.

Wall Mount Step 6: Insert Interior Container

Insert the interior container and fix it using the securing rod.