71
Beginning at front of shed, install rst row of shingles with notch at 1" past roof edge or ush with drip edge.
2
2
FRONT OF
SHED
BACK OF
SHED
BACK OF
SHED
Notch
- or -

Notch

1"
(2,5 cm)
Flush with starter row.
Flush with starter row.
Continue installing rows of
shingles by staggering at
front.
4
SHINGLES
continued...
Install second row of shingles ush at top of rst row's rain slots. Ensure 1" overhang or ush to drip edge
at front, stagger each row.
3
1"
(2,5 cm)
1"
(2,5 cm)
FRONT OF
SHED
FRONT OF SHED
Flush with rain slots.
Flush with rain slots.
Notch