72
You have  nished shingling your roof. Proceed to capping the ridge.
FINISH
Continue installing rows of shingles to the peak. At the peak make sure there is a maximum of 5" or less to the
rain slot, as shown below. If shingles overlap at ridge cut to peak with a utility knife.
Repeat steps 1 - 5 to shingle the opposite side of your roof. Trim shingles at ridge.
Once both sides are shingled you need to trim ends. Strike a chalk line 1" from edge.
Using your shingle hooked blade carefully cut shingles along chalk line.
5
6
7
8
SHINGLES
continued...

5"
(12,7 cm)
or less.
5"
(12,7 cm) MAX.

