3.1 EARTHWORK
A. Excavating and trenching and backfilling are to meet local building code.
B. Backfill per Zurn Green Turtle Installation Instructions. Pea gravel is preferred backfill material.
3.2 INSTALLATION
A. Install fiberglass interceptors according to manufacturer's installation instructions.
3.3 CONNECTION
A. Piping installation requirements are to meet local code for sanitary waste and vent piping.
Drawings indicate general arrangement of piping, fittings, and specialties.
B. Make piping connections between interceptors and piping systems.
OIL SEDIMENT WASTE INTERCEPTORS
PART I - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Oil interceptors.
1.3 DEFINITIONS
A. FRP: Fiberglass-reinforced plastic.
1.4 ACTION SUBMITIALS
A. Product Data: Include materials of fabrication, dimensions, rated capacities, retention capacities, operating
characteristics, size and location of each pipe connection, furnished specialties, and accessories.
B. Shop Drawings: For each type and size of interceptor indicated.
1. Include materials of construction, dimensions, rated capacities, retention capacities, location and size of
each pipe connection, furnished specialties, and accessories.
1.5 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Interceptors, drawn to scale, on which the following items are shown and coordinated with
each other, based on input from Installers of the items involved:
1. Interceptors.
2. Piping connections. Include size, location, and elevation of each.
3. Interface with underground structures and utility services.