Explanation: 1. Inlet valve, 2. Outlet valve, 3. Inlet hose 4. Stainless steel tube, 5. Outlet hose, 6.
Transparent vessel, 7. Bottom of the vessel, 8. Keyboard with display, 9. Button, 10 Down position,
11. Upper position, 12. Power button, 13. Connector cover
2.1
T
AKING OF SAMPLES
The device is ready for measurement at the moment of delivery.
Preceding the own measurement connect the device by fixing of inlet hose (3) to the sampling
point. The measured sample must flow through stainless tube (4) to the bottom of the vessel. The
inlet hose (3) must be secured at the sampling point not to fall out during taking of sample under
pressure.