Start-up 3
Inspection work 3.2 Page 40
© Copyright 2016 ABB. All rights reserved.
August 2017HZTL2412_ENRevision F
Check after start-up (engine at idling speed)
Lubricating system
τ Check oil pressure in oil supply lines.
τ Check oil inlet temperature.
The permissible values are listed in the section Oil supply.
Gas, air and oil lines
τ Check all gas, air and oil lines for leaks after starting the engine.
Check when running up engine
τ Measure speed, oil pressure and charging pressure at various engine
performance levels.
τ Measure exhaust gas temperature in front of and behind turbine.
τ Measure air temperature in front of and behind compressor.
The measured values must be compared with the values in the acceptance
test report, while taking different operating conditions into account.
NOTICE
Lubricants and pastes used during assembly of the turbocharger liquefy
or vaporise and might escape as an oily liquid in the first few hours after
commissioning. If oily liquid continues to escape after this period, an oil
leak must be suspected. The first step is to check for leakage of the oil
supply to the turbocharger. If this is leaky, contact an official ABB Tur-
bocharging service station.
Inspection after 100 service hours
Clean or replace lubricating oil filters after the first 100 service hours.
3.2.2
3.2.3
3.2.4

Table of Contents

Other manuals for ABB HT567872

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB HT567872 and is the answer not in the manual?

ABB HT567872 Specifications

General IconGeneral
BrandABB
ModelHT567872
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals