Figure 34: Creating a PCM600 project including several IEDs
2. Export the SCD file from PCM600.
In the Plant structure view, select the substation, right-click and select Export.
IEC09000687 V2 EN
Figure 35: Exporting SCD file from PCM600 and importing it to SAB600
3. Import the SCD configuration into the SAB600 project.
In the Project Explorer view, right-click the IEC61850 OPC Server object and
select SCL Import.
1MRS241255 B Section 4
Setting up a project
611 series 53