22
PART B Installation, Operation & Maintenance
4.2.2.5 Dismantling of Cases
4.2.2.5.1 Unpacking of Cabinet
Fig.8. Cabinet Assembly on palate
Remove top & all side covers of casing containing Cabinet
Do not remove the bottom pallet.
Assembly.
Remove Vacuum sealing
Sling
Cabinet with
drive mechanism
Fixing
bolts(2)
Fix 2 nos eye-bolts on the cabinet diagonally, remove
fixing bolts(2) and lift the cabinet.
4.2.2.4 Unpacking of Duct & Pole Assembly
Remove top & all side covers of casing containing
Hold Poles-with-Duct Assembly by lifting crane as
Remove the M8 Bolts from the rear covers of the
Remove bolts fixed to the bottom packing pallet.
Poles-with-Duct assembly.
Remove Vacuum sealing.
as shown.
Duct & open the rear cover.
Unpacking of Poles-with-Duct Assembly
Remove hardware only
after holding the assembly
by crane