ADCP-61-471 • Issue 4 • June 2000 • Section 2: Operation and Maintenance
2-52
© 2000, ADC Telecommunications, Inc.
DLP-513
Page 2 of 2
7. Hold ENABLED button down and momentarily press LMPTST/APS on the offline ODS2
module.
8. Verify that the ODS2 module that was offline is now online (its ONLINE indicator is
green) and ODS2 module that was online is now offline (its ONLINE indicator is
extinguished).
9. Verify that the APS indicator on the online ODS2 module is red indicating a forced switch
and APS disabled.
10. Slide the offline ODS2 module part way out of the chassis; this disconnects the offline
module from the chassis and ensures that data passes through the online ODS2 module only.
11. Perform end-to-end test and verify error-free data.
Reference:
DLP-510 ODS2 Distribution System and QFLC/QLX Chassis End-to-End
Tests
12. Using the ejector, press the offline ODS2 module into the chassis until it is properly seated.
13. Verify that STATUS indicator on offline ODS2 module is green and ONLINE indicator is
extinguished.
Stop! You have completed this procedure.