Do you have a question about the Airbus A318 and is the answer not in the manual?
Manufacturer | Airbus |
---|---|
Model | A318 |
Length | 31.44 m (103 ft 2 in) |
Height | 12.56 m (41 ft 2 in) |
Cabin Width | 3.70 m (12 ft 2 in) |
Service Ceiling | 12, 500 m (41, 000 ft) |
Crew | 2 |
Range | 3, 100 nautical miles |
Wingspan | 34.10 m (111 ft 11 in) |
Cruise Speed | Mach 0.78 |
Engines | 2 × CFM International CFM56-5 or Pratt & Whitney PW6000 |
Empty Weight | 39, 500 kg (87, 100 lb) |
Max Takeoff Weight | 68, 000 kg (149, 900 lb) |
Lists necessary tools and equipment for the task.
Lists related procedures and documentation for reference.
Details the necessary preparation steps for aircraft maintenance.
Step-by-step guide for removing the system pressure switch.
Lists necessary tools and equipment for the installation task.
Lists materials like hydraulic fluid and lockwire required for the task.
Lists specific parts like O-rings needed for the installation.
Lists related procedures and documentation for reference.
Details preparation steps for aircraft maintenance for installation.
Instructions to open, safety, and tag circuit breakers before maintenance.
Step-by-step guide for installing the system pressure switch.
Instructions to remove safety clips and close circuit breakers after maintenance.
Procedure to perform a leak test on hydraulic connections.
Performing an operational test of the hydraulic pressure indicating system.
Steps to return the aircraft to a serviceable condition after the task.
Steps to close access panels and doors after maintenance.
Reference to diagrams for the Blue Hydraulic System.
General safety procedures for hydraulic systems.
Procedure for depressurizing hydraulic reservoirs.
Steps to depressurize the hydraulic system before maintenance.
Details preparation steps for aircraft maintenance for the Blue system.
Instructions to open, safety, and tag circuit breakers for the Blue system.
Step-by-step guide for removing the system pressure switch for the Blue system.
Lists necessary tools and equipment for the Blue system task.
Lists materials like hydraulic fluid for the Blue system task.
Identifies work zones and access panels for the Blue system task.
Lists specific parts like O-rings for the Blue system installation.
Lists related procedures and documentation for the Blue system task.
Reference to diagrams for the Blue Hydraulic System.
Procedure to depressurize the Blue hydraulic system.
Procedure for depressurizing hydraulic reservoirs.
Procedure for pressurizing hydraulic reservoirs via ground connector.
Procedure for pressurizing hydraulic reservoirs with APU.
Operational test for Blue Hydraulic System pressure indicators.
Instructions to remove safety clips and close circuit breakers for Blue system.
Step-by-step guide for installing the system pressure switch for Blue system.
Procedure to perform a leak test on Blue hydraulic connections.
Performing an operational test for Blue hydraulic pressure indicators.
Steps to return the aircraft to a serviceable condition after Blue system task.
Reference to diagrams for Green/Yellow Hydraulic Systems.
Steps to depressurize the hydraulic system before maintenance.
Procedure for pressurizing hydraulic reservoirs via ground connector.
Procedure for pressurizing hydraulic reservoirs with APU.
Procedure to disconnect the PTU isolation coupling.
Procedure to open main gear doors for access.
Instructions to open, safety, and tag circuit breakers for the Yellow system.
Details preparation steps for aircraft maintenance for the Yellow system.
Step-by-step guide for removing the system pressure switch for the Yellow system.
Lists necessary tools and equipment for the Yellow system task.
Lists materials like hydraulic fluid for the Yellow system task.
Identifies work zones and access panels for the Yellow system task.
Lists specific parts like O-rings for the Yellow system installation.
Lists related procedures and documentation for the Yellow system task.
Reference to diagrams for Green/Yellow Hydraulic Systems.
Procedure for depressurizing hydraulic reservoirs.
Procedure for pressurizing hydraulic reservoirs via ground connector.
Procedure for pressurizing hydraulic reservoirs with APU.
Procedure to disconnect the PTU isolation coupling.
Procedure to connect the PTU isolation coupling.
Operational test for Yellow Hydraulic System pressure indicators.
Procedure to open main gear doors for access.
Procedure to close main gear doors after access.
Step-by-step guide for installing the pressure switch.
Instructions to remove safety clips and close circuit breakers for Yellow system.
Procedure to perform a leak test on Yellow hydraulic connections.
Performing an operational test for Yellow hydraulic pressure indicators.
Steps to return the aircraft to a serviceable condition.
Steps to close access panels and doors after maintenance.