- 52 -
Grid frequency is outside the limits (“Table 2” in the
appendix)
Grid voltage is outside the limits (“Table 2” in the
appendix)
Check the AC system, contact your energy
distributor.
Average grid voltage is outside the limits (“Table 2”
in the appendix)
The inverter is limiting the output power because the
grid voltage is greater than the threshold set using
the software („VPD‟ function).
The input voltage exceeds the “Maximum no-load
voltage”.
No grid voltage present. If the condition persists for
more than 1 s, the inverter will switch off.
Grid voltage or frequency are outside the limits in
the “connection” line of the regulations that envisage
it (“Table 2” in the Appendix).
Check the AC system, contact your energy
distributor.
The inverter is limiting the output power according to
the grid frequency („FPD‟ function).
The inverter has interrupted feeding due to the
emergency command received from the grid
operator.
Internal voltage is too high.
None, the inverter will restart by itself.
Internal voltage is too high.
1.5kW – 2kW version: Contact technical
assistance.
3kW version: None, the inverter will
restart by itself.
The internal bulk capacitors are not balanced.
None, the inverter will restart by itself.
The temperature is too high or the temperature
sensors are faulty.
Check requirements in the Choosing an
installation site paragraph If the inverter
displays the alarm even after a prolonged
shutdown, contact technical assistance.
The inverter does not detect one or more internal
devices.
Contact technical assistance.
Verification of PV generator isolation resistance was
negative.
Check the system if the problem persists for
a few days.
Current leakage toward grounding.
The inverter has input a DC current on the grid that
is too high.
Wait for reconnection to the grid.