TRIAD SERIES 3-PIECE BALL VALVE
Installation, Operation, and Maintenance Manual
of © BRAY INTERNATIONAL INC ALL RIGHTS RESERVED BRAYCOM The Information
contained herein shall not be copied transferred conveyed or displayed in any manner that would
violate its proprietary nature without the express written permission of Bray International Inc
INSTALLATION
Considerations
NOTICE
Certain valve constructions are uni-directional A flow arrow
will indicate the flow direction Care should be take when
installing the valve to ensure these special constructions
The valve may be fitted in any position on the pipeline
Before installing the valves the pipes must be flushed clean of
dirt burrs and welding residues or the seats and ball surface will
be damaged
If for any reason the valve is installed prior to flushing of the
piping system the valve must remain in the full open position
until the piping system has been fully flushed clean of debris
Ensure the adjoining pipe on each end of the valve is aligned to
prevent external piping loads Piping misalignment may cause
excessive external loads on the valve resulting in body joint leaks
For hydrostatic testing of the piping system the valves must be
placed in the full or half open position prior to pressurizing the
system
NOTICE
Hydrostatic system testing with the valve in the closed position
may result in damage to the valve seats aecting their ability
to create a proper seal
Failure to implement the installation and testing instructions
as outlined resulting in a valve failure will void the warranty
coverage of the product
Actuator Installation
It is recommended that the actuator package is installed to
allow sucient space for removal
It is recommended to install the actuator package with
the valve stem in the upright position If stem is in other
than vertical position actuator package weight support is
recommended to avoid any possibility of side load during
operation
It is recommended to avoid installing the actuator package
where the actuator or accessories are in contact with the
pipeline or pipeline structure
WARNING
Keep hands and other body parts clear of the valve flow port
and other rotating machinery
Prior to putting the valve into service cycle actuator to
ensure valve actuator and accessories operate properly