7 - START-UP
Preliminary checks
Checks with machine in OFF, before start-up .
For details refer to the various chapters in the manual.
√
•
safe access
•
functional spaces
•
air flow: free return and supply (no bypass, no
stratification)
•
integrity of structure
•
fans turn freely
•
unit on anti-vibration devices
•
Unit input water filter + shut-off valves for cleaning
•
Vibration isolators on water connections
•
Expansion tank (indicative volume = 5% system content)
•
Cleaned system
•
Loaded system + possibile glicole solution + corrosion
inhibitor
•
Under pressure system
•
Vented system
•
cooling circuit visual control
•
earth connection
•
unit powered by fixed network or by electrogen group
•
electric connections by customer
Start-up sequence
√
•
Powered unit
•
compressor carter heaters ON from at least 8 hours
•
phases sequence control
•
vacuum voltage measurement
•
unit ON
•
load voltage measurement and absorptions
•
fans operation check
•
treated air flow rate measurement
•
supply, return and outdoor air temperature measurement
•
subcooling and overheating measurement
•
no anomalous vibrations check
•
static pressure relief in return
•
set date and time
•
set-point customisation
•
available machine documentation
Machine start-up operations.
For details refer to the various chapters in the manual.