6.
7. Installation
and start - Service TOWER marin
7.1. Place the brewer unit on a flat, level and waterproof surface.
7.3. Connect the brewer unit to a coldwater feed -1/2"R with connection tube supplied.
NOTE! The new hose set supplied with the appliance shall be used and that old hose
sets shall not be reused. Connection to a closable valve is recommended.
Min. water pressure; 2bar (200kPa). Max. water pressure; 8bar (800kPa).
Water supply to the machine is the customer ās responsibility according to
instruction and advice from the supplier.
In areas with high level lime problem, a descaling filter should be mounted.
7.4. Electrical connection;
The brewer is not reconnectable and may only be installed to the electric supply network
with a voltage that is stated on the brewer and shall be carried out by an Authorized
Electrician.
Recommended
:
Install a line circuit breaker and a earth fault breaker to the machine.
CAUTION! Connection to a separate 3 phase only
- Brewer should be connected to 380 V with Zero and ground.
- Use 16 Amp fuses.
IMPORTANT! Electrical installations must be done of an certificated electrician.
440 V 3 - phase + ground 9000W
Observe!
See
page 13-14, Mounting machine -
Service. And how to assemble the
machine.
7.2. Install
and lock machine. See fig, A.
Adjust feets to stabilize machine.
Fig. A