Step 8: Pass the supporting tie wires or
threaded rods through the mounting
brackets (Figure 11). If using wire,
simply pass the wire through the hole
in the mounting bracket, loop back up,
and make several wraps around the
wire.
Step 9: Adjust the tension by bending the wire
with a pair of pliers. It is important not to
allow the suspended ceiling stringers to
bear the weight of the FZB.
Figure 11
NOTE: If using threaded rods, it may be necessary to
adjust the top or bottom supporting bolts/nuts.
Step 10: Ensure the FZB is level and o󰀨set
slightly from the stringers or cross-
members so that the FZB is only
slightly resting on the suspending
ceiling.
Step 11: Reinstall the ceiling panels / tiles to
complete the installation (Figure 12).
Ensure that the door is properly closed
and locked to prevent unauthorized
access and harm from the door
swinging down.
Figure 12
STANDARD RECOMMENDED PROCEDURE 003-825-AEN | ISSUE 7 | NOVEMBER 2020 | PAGE 7 OF 11