As mentioned in the paragraph on the main drive motor wiring, the pressure switch and flow switch
should be wired into the motor control circuit. By properly wiring these switches, one can be assured
of always having proper lubrication.
After complete machine installation, a check of all oil lines should be made. This is a precaution that
should be taken to assure that no damage occurred during shipment or installation.
CSI has available upon request and as an option, field service engineers on hand to direct and assist
with new machine start-ups. This gives the customer an opportunity to get direct operating
instructions from experienced personnel and to get acquainted with the men who can be made
available for inspection calls. Please arrange to notify CSI approximately three weeks before start-up
is anticipated. A fee schedule for technical support and training is available upon request.
Refer to the Installation Diagram, FIGURE II, for mounting dimensions. Keep in mind that adequate
maintenance room must be allowed for as mentioned in the above. Should further details concerning
mounting be required, consult CSI or its field representatives.