4.1. Ground connection must comply with the specific applicable regulations.
4.2. Differential switch with the correct amperage. It must comply with the specific applicable regulations (check
technical specifications of the stove).
4.3. Single-phase AC of ~230/240V – 50Hz and pure sine wave.
4.4. Easily accessible power socket. If the power socket can’t be accessed due to the characteristics of the
electrical installation, an all-pole disconnection switch must be installed.
4.5. The power cable provided by ECOFOREST is 1.4m long; you might need a longer one. Always use a cable with
ground plug and with an equal or greater section. Make sure the power cable is not placed under the stove
or close to hot or sharp surfaces that could damage it.
UNPACKING THE BOILER.
4.6. Remove the packaging and the protective plastic.
4.7. Remove the screws or bolts that fasten the stove to the pallet and remove it.
4.8. If our model has a plastic protection, it must be removed before starting it.
4.9. Remove exhaust blower protection ().The Monaco model has 3 gas output possibilities.
Airtight installation (Moon and keops): Remove protection from the air intake pipe ().
Drawing 3
Mónaco airtight installation: Fit adapter to Ø60mm.
Drawing 4
resistant to the aggressive action
of the combustion products, to
condensation and to constant
temperatures of 300 °C. The
material will comply with the
local legislation for its
application.
OBLIGATORY
ALL.
Aluminum, galvanized or iron
pipe.
PROHIBITED
ALL.
Insulated double wall pipe. OBLIGATORY
Proximity to flammable materials.
When crossing a forge or partition.
Outdoor or brick-built chimney installation.