TESTING THE LOOP
To make sure the installation of EK components was
successful, we recommend you perform a leak test for
24 hours.
When your loop is complete and filled with coolant,
connect the pump to a PSU outside of your system.
Do not connect power to any of the other components.
Turn on the PSU and let the pump run continuously. It is
usual for the coolant level to drop during this process as
air collects in the distribution plate.
Inspect all parts of the loop, and in case the coolant leaks,
fix the issue and repeat the testing process. Ensure that
all hardware is dry before the system is powered on, to
prevent any damage.