LIST OF THE SUPPLIED FOR THE STRUCTURE ASSEMBLY:
NAME OF THE COMPONENT QUANTITY
PHOTO
A PIPE 30 PCS
B PIPE 40 PCS
C PIPE 70 PCS
D PIPE 10 PCS
METAL BAND 15 PCS
FOOT 15 PCS
M12/50 SCREWS FOR LEVEL 0 AND
FRONT TRANSPARENT WINDOW
18 PCS
WASHERS FOR M12 CONSTRUCTION’S
SCREWS
62+6 PCS
M12 SCREW NUTS 62+6 PCS
TO BUILD THE FG20, FG30, FG30, FG40, FG50 YOU WILL NEED:
• 4 people,
• a ladder of a minimum 4 m height,
• a drill,
• a 19 mm automatic wrench (impact gun),
• an 8mm and a 5 mm Allen key,
• a hammer,
• 3 ropes - 15 - 20 m long each,
• a protective ground sheet at least: 6 x 4 m
(to unfold the membrane onto, before pulling
it onto the metal framework. It will protect
the membrane from getting dirty on bare ground).