First use
The pre-charge pressure should be checked and adjusted to suit the system parameters if
necessary before filling the vessel.
a. Open the bleed points (g. 6, 7).
b. Fill the installation slowly until the ll pressure in the expansion vessel is 0.3 bar higher
than the pre-charge. Bleed the system during lling (g. 8).
c. Bleed the pipe to the expansion vessel (g. 8).
d. Close the bleed points (g. 9).
e. Heat the system as high as possible for half a day and bleed regularly.
f. When the water temperature has fallen to approx. 50 °C, top up the installation to 0.5
bar above the pre-charge of the expansion vessel. Ensure that the lling hose is bled.
3. Maintenance and service
It is recommended that the expansion vessel is checked annually by approved personnel.
4. De-installation
1. Allow the installation to cool down and release the pressure from it.
2. Remove the cover cap (H) and the plug (I) (g. 10, 11).
3. Push the inner valve (J) in to drain the pressure from the expansion vessel (g. 12).
4. Unscrew the expansion vessel (A) (g. 13).
Caution: a full expansion vessel is heavy!
The water in the expansion vessel may be hot.
Observe the local regulations when you dispose of the expansion vessel.
Flexcon C/K expansion vessels are pressure equipment, and conform to Pressure
Equipment Directive 97/23/EC.
A conformity declaration can be obtained from Flamco.