999075 Revision B Page | 14 of 48
Section
Specification
Clause
Test Description
Results
Comments/ Base Standard
Configuration and Mode: Test setup standby
2.1
4.4.1
General Requirement; Risk Management
Process for ME Equipment and ME Systems
Pass
2.2
5
Identification, Marking and documents
Pass
Configuration and Mode: Test setup charging
2.3
7.1.1
Mains Terminal Disturbance Voltage
Pass
CISPR 11: 2009 A1:2010 EN 55016-2-
3: 2004 + A1:2005
2.4
7.1.1
Electromagnetic Radiation Disturbance
Pass
CISPR 11: 2009 A1:2010
EN 55016-2-3: 2004 + A1:2005
2.5
7.2.1
Harmonic Current Emissions (AC Power
Port)
Pass
EN 61000-3-2: 2014
2.6
7.2.2
Voltage Fluctuations and Flicker (AC Power
Port)
Pass
IEC 61000-3-3: 2013
2.7
Table 4
Immunity to Electrostatic discharge
(Enclosure Port)
Pass
IEC 61000-4-2 2008
2.8
Table 4
Immunity to Radiated RF Electromagnetic
fields (Enclosure Port)
Pass
IEC 61000-4-3: 2006 A2:2010
2.9
Table 4
Immunity to Proximity Fields from RF
Wireless Communicatio0n Equipment
(Enclosure Port)
Pass
IEC 61000-4-3: 2006 A2:2010
2.10
Table 5
Immunity to Surges (AC Power Port)
Pass
IEC 61000-4-5: 2005
2.11
Table 5
Immunity to Electrical Fast Transient /
Burst (AC Power Port)
Pass
IEC 61000-4-4: 2012
2.12
Table 5
Immunity to Conduct Disturbances Induced
by RF Fields (AC Power Port)
Pass
IEC 61000-4-6: 2013
2.13
Table 5
Immunity to Voltage Dips and Voltage
Variations (AC Power Port)
Pass
IEC 61000-4-11: 2004
2.14
Table 5
Immunity to Voltage Interruptions (AC
Power Port)
Pass
IEC 61000-4-11: 2004
In-Track charging system stand testing
2.7
Table 4
Immunity to Electrostatic discharge
(Enclosure Port)
Pass
IEC 61000-4-2 2008
Configuration and Mode: Test setup standby
2.4
7.1.1
Electromagnetic Radiation Disturbance
Pass
CISPR 11: 2009 A1:2010
EN 55016-2-3: 2004 + A1:2005
2.7
Table 4
Immunity to Electrostatic discharge
(Enclosure Port)
Pass
IEC 61000-4-2 2008
2.8
Table 4
Immunity to Radiated RF Electromagnetic
fields (Enclosure Port)
Pass
IEC 61000-4-3: 2006 A2:2010
2.9
Table 4
Immunity to Proximity Fields from RF
Wireless Communicatio0n Equipment
(Enclosure Port)
Pass
IEC 61000-4-3: 2006 A2:2010
Configuration and Mode: Test set up operating up and down
2.4
7.1.1
Electromagnetic Radiation Disturbance
Pass
CISPR 11: 2009 A1:2010
EN 55016-2-3: 2004 + A1:2005
2.7
Table 4
Immunity to Electrostatic discharge
(Enclosure Port)
Pass
IEC 61000-4-2 2008
2.8
Table 4
Immunity to Radiated RF Electromagnetic
fields (Enclosure Port)
Pass
IEC 61000-4-3: 2006 A2:2010
2.9
Table 4
Immunity to Proximity Fields from RF
Wireless Communicatio0n Equipment
(Enclosure Port)
Pass
IEC 61000-4-3: 2006 A2:2010
Configuration and Mode: Test setup standby
2.1
4.4.1
General Requirement; Risk Management
Process for ME Equipment and ME
Systems
Pass
2.2
5
Identification, Marking and documents
Pass
Table 3