Start-up
Initial Start-up
The initial start-up must be carried out by an authorized installer or Fröling's customer service department!
Checking the Heating System:
1. Check all electrical equipment
2. Check to see whether the heating system has been completely vented.
3. Check to see whether all the safety devices are in place and ensuring they are functioning properly.
4. Check to see whether there is sufficient ventilation and venting of the boiler room.
5. Configure and set parameters
6. Prepare the Fuel
Fill the fuel storage room with waste-wood or pellets, depending on the type of system.
IMPORTANT! The conveyor in the storage room must be switched on during the filling process
7. Pre-heating: See description page 17
Pre-heat the system at low power until the combustion chamber has dried out.
Turn the temperature controller to 70°C!