IOM GMI 2M & 2ML Nov 2010.doc
27
V: Power Connection
¾ Inspect all wiring connections to the unit and ensure they comply with all
applicable local codes.
¾ Ensure that the appropriate power supply has been connected to the unit (please
refer to the electrical rating on the unit’s nameplate).
¾ Ensure the temporary jumpers have been removed from the unit’s control panel.
¾ If applicable, ensure the external control connections have been wired.
NOTE
¾ Start-up and commissioning MUST be carried out by a GMI
qualified technician.
WARNING
The field start-up report MUST be faxed to GMI at 604-574-9572
within 10 days of start-up. Failure to do so will result in cancellation
of all expressed and/or implied warranties.
WARNING
Ensure the manual gas valve is closed prior to power being supplied
to the boiler/water heater