6. PARAMETER SETTING:
The delay from abnormal to normal or from normal to
abnormal. It is used for ATS (Automatic Transfer Switch)
control.
When mains voltage is lower the value, mains under
voltage is active.
When mains voltage is higher than the value, mains over
voltage is active.
It’s the delay from mains’ breaker open to generator’s
breaker closed or from generator’s breaker open to mains’
breaker closed.
When mains abnormal or remote start signal is active this is
the delay time of starting genset.
When mains normal or remote start signal is inactive this is
the delay time of stopping genset.
This is the number of cranking. If engine has a start failure,
genset cranks as set value times. When cranking times
finish, controller sends start fail signal.
Time of pre-powering heat plug before crank is powered
up.
Time length of cranking time.
When engine has a start fail it is the waiting time between
crankings.
Alarm for low oil pressure, high tempareture, under speed,
under frequency/ voltage, failed to charge are all checked
within this time, if it continues alarm would rise.
It is the idle running time of genset while starting.
It is the warming time between genset switch on and high
speed running.
It is the time for cooling before genset stopping.
It is the idle running time while genset stopping.