PAGE 24
MOUNTING DIMENSIONS FOR 3600 RPM STANDBY SETS 10 KW THRU 12 KW
COOLING AIR
INTO ENGINE
EXHAUST AIR OUT
MOUNTING PAD SHOULD
BE SET ON A 3" HIGH
BED OF CRUSHED GRAVEL
40" WI X 30" LG X 3" HI
OPTIONAL RE-INFORCED POLYETHYLENE
PAD. NOTE: PAD AND MOUNTING
HARDWARE IS SHIPPED LOOSE FOR
INSTALLATION BY OTHERS.
(2) MOUNTING HOLES
DOOR LOCKS & HANDLE
LOCATED ON BOTH SIDES
1/2" HIGH PITCH IN ROOF
FOR DRAINAGE OF WATER
COOLING AIR
INTO GENERATOR
DRY FUEL CONNECTION
INSTALLATION INSTRUCTIONS FOR INSTALLED GEN-SET
BASE TO FREE STANDING POLYBASE:
INSTALL (2) BOLTS THRU HOLES IN POLY BASE, AS SHOWN,
USING 5/16-18 HEX NUT TO LOCK BOLT IN PLACE. INSTALL
GEN-SET AND METAL BASE ONTO EXTENEDED 5/16-18 BOLT
AND SECURE WITH LARGE FLAT WASHER AND HEX NUT.
CAUTION: TIGHTEN NUT ONLY TO HOLD THE METAL BASE TO
PLY BASE. CONTINUED TIGHTENING WILL CAUSE METAL
BASE TO BEND INWARD.
NOTE: IF POLY BASE IN NOT USED, AND CEMENT PAD IS
REQUIRED, THE 2-BOLTS IN CEMENT PAD MUST BE 5/16-18
AND EXITED OUT FROM CEMENT, 3-1/2". USE CEMENT PAD
BOLT PLACEMENT DRAWING FOR POSITIONING THESE (2)
BOLTS.
NOTE: NOUNTING BOLTS ARE POSITIONED INSIDE LOCKED
CABINET, AS A DETERRENT TO THEFT. OUTSIDE MOUNTING
BOLTS HAVE MADE THEFT TOO EASY WHEN GAS AND
ELECTRIC LINES ARE REMOVED.
(2) 5/16-18 X 3-1/2" LG HHCS
5/16-18 HEX FLANGE NUT
AND FLAT WASHER
5/16-18 HEX FLANGE NUT
CEMENT PAD
ENGINE END