13 Servicing
13555
Diagram 13.7
13272
Diagram 13.8
13.4. Combustion Chamber and Heat
Exchanger
Remove loose debris from inside the combustion chamber
using a soft brush and vacuum cleaner.
Carefully ush by spraying water into the heat exchanger, any
remaining debris should pass through the condensate trap
(Ensure the water is kept away from electrical components).
13.5 Inner Casing Panel Seal check
Check the condition of the seal, if worn or damaged remove
the seal and thoroughly clean the casing surface before tting
the new seal, see diagram 13.8.
Ret the inner casing panel.
NOTE: Ensure the seal is tted correctly giving an airtight
joint.
13.6 Service Completion
Re-check the combustion as described at the beginning of
this section.
On completion of the service the “Benchmark” Service Record
should be completed.
NOTE: If the burner is not to be serviced, do not perform the
following instructions 13.5, 13.6, 13.7 and 13.8 but continue to
section 13.9 to complete the servicing.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Glow-worm 24cx and is the answer not in the manual?

Glow-worm 24cx Specifications

General IconGeneral
Model24cx
ManufacturerGlow-worm
CategoryBoiler
TypeCombi
Output24 kW
CH Output (kW)24kW
Max Working Pressure3 bar
Dimensions740 x 418 x 300 mm
FuelNatural Gas

Related product manuals